Intelligent
Enterprise
November
1998
Measure
Early, Measure Often
Richard Winter
In VLDB projects, it is essential to begin testing
for scalability and performance early in the development process.
If you are venturing into unexplored territory, you must measure
scalability and performance before you commit to a platform or
an implementation approach.
The "Usual"
Figure 1 illustrates the usual approach. If you just "do
what comes naturally," you will select the platform, design
the database, and write the applications before you get around
to testing for performance. But when you employ the approach
depicted in Figure 1 (page 82), you are assuming that performance
and scalability are secondary issues. And you are assuming that
modest adjustments in platform configuration and database design
can be employed in the last stages of testing to overcome any
performance problems.
Figure 1. Ordinary database
application development.
Extreme Development
In VLDB projects, however, the system is so large or the engineering
challenge so extreme that you must deal with performance and
scalability earlier in the cycle. Figure 2 shows how the development
process differs in these extreme VLDB projects.
Figure 2. VLDB application
development.
In an extreme VLDB project, you need to consider that your
usual database or system platform may not meet engineering requirements;
the requirements as you state them may be beyond the capabilities
of any off-the-shelf product. You must also consider that different
database products may perform very differently on the application.
The difference in performance -- or price/performance -- between
one product and another could be a factor of 100 or more. Similarly,
the difference in performance -- or price/performance -- between
one database design and another could be a factor of 100 or more.
Finally, in an extreme VLDB project, you must consider that
there are no good models for predicting performance. If you want
to manage the engineering risks in your project appropriately
-- those concerned with performance, availability, and scalability
-- you must measure; and if you are going to act on the results
of your measurements before it's too late, you must measure early.
The VLDB Performance Management Approach
There are two problems with measuring early in the process:
The system doesn't exist yet, and you have incomplete knowledge
of its performance and workload requirements. But the alternative
approach -- not measuring at all -- results in unacceptable risks.
Therefore, the best approach is iterative. You first estimate
the requirements and workload, then measure. Next, taking the
uncertainties in your measurements into account, you make the
best decisions you can at that point in the process and move
to the next stage of development. Then you repeat the process.
At each stage, your information is better and your decisions
can be firmer.
Remarkably, even early stage measurements based on incomplete
and uncertain information can be extremely valuable. And they
are often the key to avoiding disaster. Beyond that, the very
process of iterating on the estimation of performance requirements,
the measurements of candidate solutions, and the application
of measurement results to implementation leads to insights about
performance, scalability, and availability and increases the
prospects for success.
How Extreme is Your Project?
Some key issues for many project managers are: How extreme
are my database requirements? Am I really trying to do something
that hasn't been done before? Is it really so important that
I engage in an early stage measurement process that will take
resources and delay the start of "real work?"
I recommend finding out how the key dimensions of your implementation
compare to those already in production. If you are significantly
beyond the frontier, then you are in a high-risk situation and
you need to measure before you get committed. Among the dimensions
you may want to evaluate when you assess your position are: database
size, largest table, row size, number of rows, workload volume,
type of workload, your intuitive assessment of data and query
complexity, number of concurrent users, transaction rate (OLTP),
number of queries in-flight, performance requirements, availability
requirements, batch update workload, and online update workload.
If you find that you are significantly beyond prior experience
in any dimension or meaningful combination of dimensions, proceed
with care. Figure 3 illustrates the frontier for the combination
of database size and queries in-flight for decision-support systems.
Figure 3. The DSS frontier
for database size and queries in flight (source: Winter survey
of Very Large Databases, Winter Corporation, Waltham, MA).
Each point plotted on the graph (represented by small squares)
indicates a decision-support system in production. The two points
marked with a "blue ribbon" symbol were those found
to have the largest value in a category in Winter Corp's VLDB
Survey. Thus, in the upper left, Kmart had 800 in-flight queries.
In the lower right, Sears had a database size of 4.6TB.
The dark area represents the "frontier," that part
of the space beyond which there is no significant production
experience. If your requirements fall at or near the frontier,
you should probably measure early. The gray shaded area is "beyond
the frontier" -- well beyond any significant production
experience. If your requirement falls in the gray shaded area,
you must measure before you get too far into the development
process.
A general guideline is that if two or more dimensions of your
system size seem critical and are intuitively related, look at
them together in terms of the VLDB frontier. With more than three
dimensions, it's easier to work with a tabular rather than a
graphical representation of the data.
In Figure 3, there is one system operated by Fidelity that
falls in the middle of the graph. If that system had requirements
similar to yours, you would give it additional weight. In answering
this question, it's important to look at the nature of the application
and the feel of the query set as well as the quantitative factors,
but it's usually not a good idea to consider a single system
to have changed the shape of the frontier.
Also, recognize that the frontier changes rapidly as technology
advances and new systems come into production, so no one source
of information is complete. The Winter Survey (see www.wintercorp.com)
is a good starting point, but you should supplement it with private
inquiries because data about some systems is kept confidential.
Vendors are usually prepared to provide additional data points.
Just be sure you verify them directly with the database owner,
take particular care to use consistent measures for all data
points, and make sure you learn the status of the system. Some
vendors routinely describe some systems that are really only
in test or in pilot use as "production" systems.
"Production status" is extremely important at or
beyond the frontier because even experienced users get surprised
and back off in late testing stages. Frequently, problems in
performance, availability, or scaling surface only days or weeks
before production operation begins. Sometimes they surface early
in production. So the system isn't in production until it's actually
in production or unless it stays in production. Even then, it's
not really in production unless it is in heavy use, or clearly
progressing toward its intended level of use.
Defining Your Benchmark
After your risk assessment convinces you that you should perform
a measurement, then what do you do? You must specify a benchmark
that you can apply and refine at various stages of the project.
A famous politician said that the best approach to getting elected
was to have your supporters vote "early and often."
Similarly, the best approach to VLDB development is to measure
early and often -- and keep doing so throughout development and
production.
To define a benchmark, you must define a database workload,
a database concept, and a set of operational requirements. To
address scalability, you must define these factors as you believe
they will exist at multiple points in the future.
For performance measurement purposes, the database concept
is a rough description of the 20 to 40 entities in the database
that are expected to figure most significantly in either data
volumes or transaction volumes. This description needs to include
only estimated row count, estimated row size, estimated number
of columns, primary keys, foreign keys, and columns to use to
a significant extent in data selection. For the last three items,
the description needs to include an estimate of the distribution
of data values over the rows. The workload definition comprises
your best estimate of the nature, frequency, and distribution
of the SQL requests your system will need to process.
Uncertainty clouds many of the factors that contribute to
an accurate picture of the database and the workload early in
the project. This uncertainty is unavoidable, but if you make
a reasonable estimate of the workload requirements and measure,
you are much better off than if you don't. You can often deal
with the uncertainty by simplifying assumptions. You don't simplify
away the database performance requirement, but you can often
ignore factors that primarily concern application logic or user
interface. Usually, it is at least possible to come up with reasonable
estimates of the "lowest likely" and "highest
likely" values. Then in the worst case, you can measure
both and manage the risks accordingly.
Applying Your Benchmark Definition
When you have defined your benchmark, you are in a position
to take a variety of positive actions. You can compare it to
standard benchmarks and determine whether any standard benchmark
data might contribute to your analysis. If you are about to do
a platform acquisition, you can build the benchmark into the
acquisition process. If you have a platform, you run the benchmark
to gain information about how your application is likely to perform
and employ the results to shape and support decisions concerning
configuration, database design, or implementation.
The point is that a benchmark definition provides the tool
you need for rational decision making about performance and cost
throughout the project lifecycle. Without it, you have only guesswork
and opinion. With it, you have the means to get or keep your
project on the right track. You have a tool to manage your systems'
performance. In the early stages of the project, it is a blunt
tool, but it is crucial for avoiding disaster in the early decisions.
And as it is refined with better information as the project unfolds,
it becomes a sharper tool with ever increasing power to help
your effort succeed. |